TOP
Work Continues on the Foundations for the New NY Bridge
Press Release March 7, 2014 No Comments

Work Continues on the Foundations for the New NY Bridge

March 7, 2014

Tappan Zee Constructors, LLC (TZC) continues construction of the New NY Bridge the week of March 10. This construction includes pile driving operations between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays.

A second shift of workers also continues to work on the permanent foundation piles.

Work continues closer to shorelines on both the Rockland and Westchester temporary trestles, including daytime pile driving to install the temporary foundation piles needed to support the platform. The trestles are work platforms that will support cranes for the construction of the eastern- and western-most sections of the new bridge.

LANE CLOSURES FOR NEW YORK STATE THRUWAY (I-87/I-287)
Monday March 10 Northbound, Right Lane Near Exit 9 10 a.m. to 3 p.m.
Monday March 10 Northbound, Right Lane of the TZB 8 p.m. to 6 a.m.
Tuesday March 11 Southbound, Right Lane Near Exit 10 10 a.m. to 2 p.m.
Tuesday March 11 Northbound, Right Lane of the TZB 8  p.m. to 6 a.m.
Wednesday March 12 Northbound, Right Lane Near Exit 9 10 a.m. to 3 p.m.
Wednesday March 12 Northbound, Right Lane of the TZB 8  p.m. to 5 a.m.
Thursday March 13 Northbound, Right Lane near exit 9 10 a.m. to 3 p.m.
Thursday March 13 Northbound, Right Lane of the TZB 8  p.m. to 6 a.m.
Friday March 14 Northbound, Right Lane of the TZB 8  p.m. to 6 a.m.

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge, weather permitting. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. The U.S. Army Corps of Engineers has issued a modified permit for additional temporary mooring locations during construction of the new bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information and the modified mooring permit map can be found on the project website at NewNYBridge.com under the “Boater Safety” icon.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Rockland access ramp modifications
  • River Road utility work
  • Test pile program
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Clearing and grubbing on Westchester landing area
  • Clearing and grubbing on Rockland landing area