Three 20 Minute Stops of Northbound Thruway in Tarrytown to Occur Overnight Tonight
Press Release November 14, 2014 No Comments

Three 20 Minute Stops of Northbound Thruway in Tarrytown to Occur Overnight Tonight

November 14, 2014

Three Stops on Thruway to Occur Overnight Tonight
Traffic stops up to 20 minutes each on the northbound lanes of the New York State Thruway (I-87/I-287) near exit 9 (Tarrytown – Sleepy Hollow – US Route 9) will occur this overnight, Friday, Nov. 14, to allow removal of a sign gantry that extends over the northbound Thruway. The stops will take place between 11:59 p.m., Friday, Nov. 14 and 4 a.m., Saturday, Nov. 15.

To ensure the safety of the public, New York State Police will stop and hold all traffic approaching the gantry removal operation immediately before the closures go into effect. Motorists will be permitted to enter the Thruway from all open ramps during the closures. Travelers are advised that delays are likely on the northbound Thruway during the overnight operation.

Additionally, the gantry removal will leave just one travel lane open from 11:59 p.m., Friday, November 14 to 6 a.m., Saturday, Nov. 15, and that single lane will be subject to closure detailed above. The two southbound high speed E-ZPass lanes at the Tarrytown toll plaza will be closed during this period as well. The gantry removal will also entail the closure of the northbound exit 9 on-ramp from 9 p.m., Friday, Nov. 14 to 6 a.m., Saturday, Nov. 15. Motorists who would normally use the ramp to access the northbound Thruway will be detoured approximately 1.5 miles east on Route 119/White Plains Road to exit 8A in Elmsford (see detour map below):

Lanes to Shift on Southbound Thruway Near Rockland Landing Next Week
Southbound lanes of the Thruway near exit 10 (Nyack – South Nyack – US Route 9W) will shift slightly on Monday, Nov. 17 to allow for construction of a temporary all-electronic toll collection (AETC) gantry. Crews will construct and test the AETC system over the next six months in preparation for the eventual removal and reconstruction of the Westchester toll plaza.

Work to commence on Stormwater Management Pond South of Thruway in Tarrytown
Tappan Zee Constructors, LLC (TZC) will begin clearing a work zone immediately south Thruway in Tarrytown to prepare for the construction of a stormwater management pond. The pond will help control the flow of stormwater by collecting and retaining runoff. Excavation will follow the clearing and a retaining wall will be installed next spring. TZC will continue to employ noise, dust and other mitigation techniques to minimize impacts to local residents.

Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge
A small section of the existing Tappan Zee Bridge’s Westchester landing will be removed during overnight hours next week to make room for the new bridge. The work will require the closure of the northbound Thruway’s two right traffic lanes approaching the bridge to construct the abutment and the first foundation pier for the new northbound bridge, which is due to be completed late 2016. Closures will occur at varying times during the following overnights:

START CLOSURE END
10 p.m., Friday, Nov. 14 Northbound two right lanes approaching the bridge. A third lane will be closed at 11:59 p.m. 8 a.m., Saturday, Nov. 15
8 p.m., Saturday, Nov. 15 Northbound two right lanes approaching the bridge. A third lane will close to at 11:59 p.m. 9 a.m., Sunday, Nov. 16
8 p.m., Monday, Nov. 17 Northbound two right lanes approaching the bridge. A third lane will be closed at 11 p.m. 4:30 a.m., Tuesday, Nov. 18
8 p.m., Tuesday, Nov. 18 Northbound two right lanes approaching the bridge 4:30 a.m., Wednesday, Nov. 19
8 p.m., Wednesday, Nov. 19 Northbound two right lanes approaching the bridge 4:30 a.m., Thursday, Nov. 20
9 p.m., Thursday, Nov. 20 Northbound two right lanes approaching the bridge 4:30 a.m., Friday, Nov. 21
10 p.m., Friday, Nov. 21 Northbound two right lanes approaching the bridge 8 a.m., Saturday, Nov. 22

 

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations.

Related to the Westchester landing work referenced above, work is continuing on the new bridge’s landings on both sides of the river.  In Westchester, work includes drilling holes into the bedrock for the foundation of the landing. In Rockland, a similar operation is improving the strength of the soil by using aggregate piers, which are constructed with a drill that mixes soil and aggregate (i.e., crushed stone) to form a strong base for the new bridge’s abutment and foundation. The drilling process is less audible than impact pile driving and noise-reducing measures are being implemented to further minimize sound levels. The eight-week operation is anticipated to conclude in November.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit https://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.