TOP
Testing Of Cashless Tolling Facility Continues Overnight Lane and Ramp Closures on Southbound Thruway (I-87/I-287)
Press Release February 25, 2016 No Comments

Testing Of Cashless Tolling Facility Continues Overnight Lane and Ramp Closures on Southbound Thruway (I-87/I-287)

February 25, 2016

As weather permits, field testing of the project’s temporary cashless tolling system in Rockland will continue throughout the coming week near on-ramps to the southbound New York State Thruway (I-87/ I-287) at exit 10 (Nyack – South Nyack – US Route 9W) and exit 11 (Nyack – South Nyack – US Route 9W).

The testing of the system, also known as all-electronic toll collection, will necessitate closing the on-ramps during the overnights of Thursday, Feb. 25, through Saturday, Feb. 27, and Monday, Feb. 29, through Saturday, Mar. 5. Drivers will be directed to use the exit 12 (West Nyack – NY Route 303 – Palisades Center Drive) on-ramp from Route 303 in West Nyack, as shown in the graphic below. Signs will be posted to advise motorists of the detour route.

In addition, the work will require the overnight closure of up to three lanes of the southbound Thruway during the coming week. Specific lane and ramp closure times are detailed in the chart below.

The AETC system is expected to be activated this spring.

 

Rockland_OnRamp_2016_01_28v2

LANE AND RAMP CLOSURES NEAR THE TAPPAN ZEE BRIDGE
DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 2/25 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Fri., 2/26 Southbound Thruway
from exit 12 to exit 10
Thu., 2/25 9 p.m. – On-ramp closures 5 a.m., Fri., 2/26 Southbound
exit 10 and 11
Fri., 2/26 9 p.m. – Two right lanes
12 a.m. – Three right lanes
6 a.m., Sat., 2/27 Southbound
from exit 12 to exit 10
Fri., 2/26 10 p.m. – On-ramp closures 6 a.m., Sat., 2/27 Southbound
exit 10 and 11
Sat., 2/27 9 p.m. – Two right lanes
12 a.m. – Three right lanes
6 a.m., Sun., 2/28 Southbound
from exit 12 to exit 10
Sat., 2/27 10 p.m. – On-ramp closures 6 a.m., Sun., 2/28 Southbound
exit 10 and 11
Mon., 2/29 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Tue., 3/1 Southbound
from exit 12 to exit 10
Mon., 2/29 9 p.m. – On-ramp closures 5 a.m., Tue., 3/1 Southbound
exit 10 and 11
Tue., 3/1 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Wed., 3/2 Southbound
from exit 12 to exit 10
Tue., 3/1 9 p.m. – On-ramp closures 5 a.m., Wed., 3/2 Southbound
exit 10 and 11
Wed., 3/2 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Thu., 3/3 Southbound
from exit 12 to exit 10
Wed., 3/2 9 p.m. – On-ramp closures 5 a.m., Thu., 3/3 Southbound
exit 10 and 11
Thu., 3/3 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Fri., 3/4 Southbound
from exit 12 to exit 10
Thu., 3/3 9 p.m. – On-ramp closures 5 a.m., Fri., 3/4 Southbound
exit 10 and 11
Fri., 3/4 9 p.m. – Two right lanes
12 a.m. – Three right lanes
6 a.m., Sat., 3/5 Southbound
from exit 12 to exit 10
Fri., 3/4 10 p.m. – On-ramp closures 6 a.m., Sat., 3/5 Southbound
exit 10 and 11
Sat., 3/5 9 p.m. – Two right lanes
12 a.m. – Three right lanes
6 a.m., Sun., 3/6 Southbound
from exit 12 to exit 10
Sat., 3/5 10 p.m. – On-ramp closures 6 a.m., Sun., 3/6 Southbound
exit 10 and 11

Demolition of Former Maintenance Facility
Tappan Zee Constructors, LLC (TZC) concluded above-ground demolition of the New York State Thruway Authority’s former maintenance offices in Tarrytown this week. Crews will now excavate the building’s underground foundations and garage facilities.

Bridge maintenance teams currently operate from a temporary facility near exit 12 in West Nyack. The demolition will make way for a new maintenance facility /office building, which will begin construction this spring.

Noise Barrier Construction
TZC will continue constructing noise barriers along the Thruway in South Nyack next week. The work includes constructing noise barrier foundations along the southbound Thruway between the South Broadway bridge and River Road. After the foundations are established, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

TZC will also continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months.

Additional work includes:

  • Main span tower construction
  • Support for river-based work from the Rockland trestle
  • Rockland landing retaining walls
  • Survey inspections on the existing bridge
  • Westchester landings utility work
  • Girder assembly placement
  • Bridge road deck installation
  • Drainage structure installations

Boater Safety
Marine units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit https://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.