Tappan Zee Constructors, LLC (TZC) is scheduled to continue overhead gantry improvements this week. The work requires overnight lane closures on the southbound New York State Thruway (I-87/I-287). Specific lane closure times are listed in the chart below.
DATE: | CLOSURES BEGIN: | CLOSURES END: | LOCATION: |
Mon. 7/8 | 8 p.m. – Two right lanes 11 p.m. – Three right lanes |
5 a.m., Tues. 7/9 | Southbound (I-87/I-287) from exit 11 on to the bridge |
Tues. 7/9 | 8 p.m. – Two right lanes 11 p.m. – Three right lanes |
5 a.m., Wed. 7/10 | Southbound from exit 11 on to the bridge |
Wed. 7/10 | 8 p.m. – Two left lanes 11:59 p.m. – Three left lanes |
5 a.m., Thur. 7/11 | Southbound from exit 11 to exit 9 |
Thur. 7/11 | 9 p.m. – Two left lanes 11:59 p.m. – Three left lanes |
5 a.m., Fri. 7/12 | Southbound from exit 11 to exit 9 |
Fri. 7/12 | 10 p.m. – Two right lanes | 7 a.m., Sat. 7/13 | Southbound from the bridge to exit 9 |
The New York State Thruway Authority provides this information as a public service. Any reliance you place on such information is therefore strictly at your own risk. Nothing in these guidelines shall supersede the actual construction conditions, and regulations set forth by the U.S. Coast Guard.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.