No Pile Driving Scheduled for Thanksgiving Holiday
Press Release November 27, 2013 No Comments

No Pile Driving Scheduled for Thanksgiving Holiday

November 27, 2013

No pile driving activities are scheduled for the New NY Bridge project on Thanksgiving Day, Thursday, Nov. 28, but work on the new main span continues Friday and Saturday.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website under the “Boating Safety” icon.

Ongoing operations:

  • Rockland access ramp modifications
  • Armoring of dredge channel
  • River Road utility work
  • Test pile program
  • Rockland Dock Extension – finishing work under existing bridge
  • Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Reinforcement steel pre-assembly at bridge yard