Tappan Zee Constructors (TZC) is scheduled to proceed with the installation of road deck panels for the new bridge’s eastbound span over River Road at the Rockland landing. The work…
Tappan Zee Constructors (TZC) is scheduled to continue installing steel girders for the Governor Mario M. Cuomo Bridge over River Road at the Rockland landing. The materials connect the eastbound…
Governor Andrew M. Cuomo today announced the 532-foot-long center span of the retired Tappan Zee Bridge – the first of five main span sections – began the process of being…
Tappan Zee Constructors (TZC) is preparing to install steel girders and concrete deck panels for the Governor Mario M. Cuomo Bridge over River Road at the Rockland landing. The materials…
The installation of precast concrete slabs near the bridge’s Westchester landing will now require an overnight closure of the northbound New York State Thruway (I-87/I-287) exit 9 (Tarrytown – Sleepy…
Tappan Zee Constructors (TZC) is scheduled to continue installing new precast concrete slabs near the bridge’s Westchester landing. The work will create a new base roadway for the twin-span crossing’s…
Tappan Zee Constructors (TZC) is scheduled to remove large steel truss sections of the old bridge next week with the assistance of the project’s largest crane, dubbed I Lift NY….
Tappan Zee Constructors (TZC) is scheduled to continue installing new precast concrete slabs near the bridge’s Westchester landing. The work will create a new base roadway for the twin-span crossing’s…
Tappan Zee Constructors (TZC) continues to prepare roadway sections of the northbound New York State Thruway (I-87/I-287) for removal near the bridge’s Westchester landing. This will allow TZC to install…
Tappan Zee Constructors (TZC) is scheduled to begin preparation work next week to remove roadway sections of the northbound New York State Thruway (I-87/I-287) near the bridge’s Westchester landing. This…