Tappan Zee Constructors, LLC will continue utility work on River Road in South Nyack. This work will continue through November and will involve reducing the roadway to one lane during…
Tappan Zee Constructors, LLC will begin utility work on River Road in South Nyack the week of Sept. 9. This work will continue through November and will involve reducing the…
Tappan Zee Constructors, LLC (TZC) will not engage in any pre-construction activities that affect traffic through Monday, Sept. 2 in observance of Labor Day. No lane closures will be allowed…
Work is scheduled to begin the week of August 26 on the Rockland trestle, which is the second temporary work platform to be constructed as part of the New NY…
Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program. These load tests are performed to ensure piles…
Tappan Zee Constructors, LLC (TZC) will continue 24-hour-a-day dredging operations in the Hudson River as part of the New NY Bridge Project. The U.S. Coast Guard has issued a revised…
Tappan Zee Constructors, LLC (TZC) began 24 hour a day dredging operations today in the Hudson River as part of the New NY Bridge Project. The U.S. Coast Guard has…
Tappan Zee Constructors, LLC (TZC) will begin around-the-clock dredging operations in the Hudson River today and will continue dredging over the next three months as part of the New NY…
Tappan Zee Constructors, LLC (TZC) is scheduled to begin impact pile driving as part of the ongoing test pile operation this week. The test pile installation will continue over the…
Construction of the Rockland Bulkhead will begin next week as crews enlarge the work platform in the New York State Thruway Authority’s Rockland maintenance area located on River Road in…