Tappan Zee Constructors, LLC (TZC) will continue constructing the New York State Thruway’s (I-87/I-287) temporary all-electronic toll collection system next week by installing foundations for the overhead gantry on right…
Tappan Zee Constructors, LLC’s (TZC) two floating concrete batch plants recently returned to the work site, passed the required testing and soon will begin pumping concrete. The batch plants were…
The exit 10 on-ramp to the southbound New York State Thruway (I-87/I-287) in South Nyack will be closed from 9 p.m., Tuesday, Mar. 17 to 5 a.m., Wednesday, Mar. 18….
Road-striping work will require the closure of three lanes of the northbound New York State Thruway (I-87/I-287) from exit 8A (Elmsford – NY Route 119 – Saw Mill River Parkway…
Two lanes of the southbound New York State Thruway (I-87/I-287) in Tarrytown will be closed between 7 p.m. and 6 a.m. during every overnight next week (Monday evening, Mar. 9…
The Exit 10 on-ramp to the southbound New York State Thruway (I-87/I-287) in South Nyack will be closed from 9 p.m., Friday, Mar. 6 to 5 a.m., Saturday, Mar. 7….
Tappan Zee Constructors, LLC (TZC) will begin clearing slopes adjacent to the southbound New York State Thruway (I-87/I-287) in South Nyack near exit 10 starting Monday, Feb. 23. The work…
No construction work is scheduled for President’s Day, Monday, Feb. 16 on the New NY Bridge project. Freezing temperatures and winter weather in the Hudson Valley will continue to limit…
Two lanes of the southbound New York State Thruway (I-87/I-287) in Tarrytown will be closed between 7 p.m. and 6 a.m. during every overnight next week (Monday evening, Mar. 9…
Following a pause in construction due to Winter Storm Juno, Tappan Zee Constructors, LLC (TZC) is continuing to assemble formwork that will shape the bridge’s landings on the Rockland and…