Tappan Zee Constructors, LLC (TZC) will begin installing a new drainage system under the westbound/northbound New York State Thruway (I-87/I-287) this week. The month-long operation will require regular overnight lane…
Tappan Zee Constructors, LLC (TZC) continues to install the new northbound bridge’s stay cable system. TZC has installed the first four stay cables on the main span towers, and is…
Tappan Zee Constructors, LLC (TZC) continues to install the new northbound bridge’s stay cable system. The stay cables are comprised of numerous metal strands, tightly packed in a protective sheath….
Tappan Zee Constructors, LLC (TZC) has begun installing road deck panels for the new bridge’s Westchester approach. Project cranes will lift the prefabricated deck panels into place atop the previously…
All Lanes Will Reopen to Traffic at 5:30PM Today Governor Andrew M. Cuomo today announced that all seven lanes on the Tappan Zee Bridge will open to traffic just days…
The New York State Thruway Authority today announced that Tappan Zee Constructors, LLC (TZC) has completed installation of the first stay cables on the New NY Bridge project. The stay…
Work Scheduled to Begin Tonight, July 21 at 8 p.m. and be Completed by 5 a.m. — in Time for Morning Commute Tomorrow, July 22 Delays Expected on Southbound I-87/…
At Governor Cuomo’s direction, six out of seven lanes on the Tappan Zee Bridge have been reopened to traffic ahead of schedule following a crane accident earlier today. Three lanes…
The I Lift NY super crane continues to install structural steel girders for the Rockland approach this week. A total of 31 miles of steel girders cumulatively weighing more than…
The I Lift NY super crane continues to install structural steel girders for the Rockland approach this week. A total of 31 miles of steel girders cumulatively weighing more than…