Last week saw completion of the second of the New NY Bridge project’s two main span pile caps. More than 20,000 cubic yards of concrete were used to fill the…
The New NY Bridge project has made extraordinary progress since construction operations began in 2013. Now with steel-reinforced foundations and concrete piers in place, the project continues to move forward…
The New NY Bridge took another leap forward this week with the installation of the first structural steel on the new bridge’s westbound (northern) span. The 390-foot segment of steel…
By the sweat of their brow, construction workers have made impressive progress on the New NY Bridge project. But with near triple digit temperatures increasingly becoming the norm, keeping more…
The incredible progress on the New NY Bridge project is becoming more and more visible every day. Residents are literally seeing engineering history in the making. As part of their…
Steel bars that reinforce the new bridge’s concrete structures are coated with a protective zinc coating. Over 60 million pounds of steel bars will fortify the new bridge, more than…
Rockland County’s Marine 2 is one of many patrol units monitoring the construction zone and encouraging all boaters to obey established U.S. Coast Guard safety protocols. With the 2015 recreational…
The new bridge’s first steel girder assembly is raised into its permanent location by the I Lift NY super crane. Following months of careful planning and with the use of…
A third floating concrete batch plant arrives on the New NY Bridge project site. The addition of a third floating concrete batch plant this week enables the New NY Bridge…
After a stunningly beautiful trip down the Hudson River, the first 12’ tall, 400’ long section of structural steel arrived at the New NY Bridge construction site on Thursday June…