TOP
Girder Installation Continues at Westchester LandingNew Animation Shows How Work Will Safely Progress
Press Release October 15, 2015 No Comments

Girder Installation Continues at Westchester LandingNew Animation Shows How Work Will Safely Progress

October 15, 2015

Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girders for the new bridge’s Westchester landing in Tarrytown next week. The girders will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. To install girder assemblies, TZC is literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation.  As the operation progresses, additional girders will be connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

While the entire operation is anticipated to take approximately three months, work over the Metro-North tracks will occur during three Friday overnights during the remainder of the year. The first will occur on Oct. 23, with the two remaining dates still yet to be set in November and December. When the overnight work is scheduled, advance notice will be given to help Metro-North riders plan accordingly. Metro-North will adjust its schedule slightly on those nights to allow the work to be completed. TZC will suspend construction activities when trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

Across the river, TZC also will continue installing steel girders near the South Nyack shoreline. Safely accomplishing the work will require reducing River Road to one lane during weekdays between 6 a.m. to 5 p.m. Flag persons will keep traffic moving by alternating the directional flow between north and south.

Smaller girder sections will be lifted into place by cranes from the Rockland trestle in South Nyack. Ironworkers then bolt together the girders and cross beams that will support the new bridge’s concrete road deck. In deeper water, the I Lift NY super crane will continue placing larger girders, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland County will continue with the installation of equipment on an overhead gantry above the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work necessitates closing the on-ramp during the overnight of Friday, Oct. 23. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. The work also requires overnight double-lane closures tonight, Oct. 15 and tomorrow, Oct. 16 as well next Monday, Oct. 19 through Thursday, Oct. 22. A triple-lane closure is planned for on Friday, Oct. 23. Specific lane and ramp closure times are listed in the chart below.

RC_OnRamp_Exit10_Final

LANE AND RAMP CLOSURES NEAR THE TAPPAN ZEE BRIDGE
DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 10/15 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Fri., 10/16 Southbound I-87/I-287
from exit 12 to exit 10
Fri., 10/16 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Sat., 10/17 Southbound
from exit 12 to exit 10
Mon., 10/19 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Tue., 10/20 Southbound
from exit 12 to exit 10
Tue., 10/20 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Wed., 10/21 Southbound
from exit 12 to exit 10
Wed., 10/21 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Thu., 10/22 Southbound
from exit 12 to exit 10
Thu., 10/22 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Fri., 10/23 Southbound
from exit 12 to exit 10
Fri., 10/23 9 p.m. – One right lane
10 p.m. – Two right lanes
11 p.m. – Three right lanes
8 a.m., Sat., 10/24 Southbound
from exit 12 to exit 10
Fri., 10/23 10. p.m. – Ramp Closure 5 a.m., Sat., 10/24 Southbound
exit 10 on-ramp

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Installation of Noise Barriers in South Nyack
Next week will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit https://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.