TOP
Foundation Work Continues to Progress on the New NY Bridge
Press Release April 4, 2014 No Comments

Foundation Work Continues to Progress on the New NY Bridge

April 4, 2014

Several of the pile groups that will form the foundation for approach piers for the New NY Bridge have been completed as Tappan Zee Constructors, LLC (TZC) continues to make progress on the project.

Marine crews are working from the shorelines of Rockland and Westchester counties, moving outward to place permanent foundation piles. Work on the foundations for the main span continues to progress as well. To learn more about the main span foundation and tower construction see the new “Bridge Rising” animation on NewNYBridge.com.

The foundation construction includes pile driving operations between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays. A second shift of workers continues welding work on the permanent foundation piles.

Work continues closer to shorelines on both the Rockland and Westchester temporary work trestles, including pile driving to install the temporary foundation piles needed to support the platform. The trestles are work platforms that will support cranes for the construction of the eastern- and western-most sections of the new bridge.

LANE CLOSURES FOR NEW YORK STATE THRUWAY (I-87/I-287):
Monday April 7 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Monday April 7 Southbound, Right Lane near Exit 9 10 a.m. to 3 p.m.
Tuesday April 8 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Tuesday April 8 Southbound, Right Lane near Exit 9 10 a.m. to 3 p.m.
Wednesday April 9 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Thursday April 9 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Friday April 10 Northbound, Right Lane near Exit 10 10 a.m. to 1 p.m.

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge, weather permitting. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has extended its Regulated Navigation Area (RNA) around the project site to 500 yards north and 500 yards south of the existing bridge. Boaters are advised to proceed with no wake at a maximum speed of five knots in this area, and to transit the main channel when traveling between the north and south sides of the bridge. The RNA also allows the Coast Guard to limit or prohibit marine traffic in those areas if necessary. The New York State Thruway Authority and TZC have also applied for a new safety zone around the 16 construction barge mooring locations at the site. No vessel traffic will be allowed in the safety zone. The Coast Guard boating safety information and the modified mooring permit map can be found on the project website at NewNYBridge.com under the “Boater Safety” icon. 

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Rockland access ramp modifications
  • River Road utility work
  • Test pile program
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Clearing and grubbing on Westchester landing area
  • Clearing and grubbing on Rockland landing area