TOP
Foundation Work Continues on the New NY Bridge
Press Release May 30, 2014 No Comments

Foundation Work Continues on the New NY Bridge

May 30, 2014

Construction of the New NY Bridge continues the week of June 2 with pile driving between 7 a.m. and 7 p.m., Tuesday through Friday.  A second shift of workers will also continue pile welding operations associated with permanent foundations.

Marine crews are working from the shorelines of Rockland and Westchester counties, moving outward to place permanent foundation piles. Work on the foundations for the main span will continue as well. To learn more about the main span foundation and tower construction see the new “Bridge Rising” animation on NewNYBridge.com

Work will also continue on the Rockland work trestles near the county shorelines, including pile driving to install the temporary foundations needed to support the platforms. The trestle will support cranes for the construction of the western-most sections of the new bridge.

LANE CLOSURES FOR NEW YORK STATE THRUWAY (I-87/I-287):
Monday June 2 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Tuesday June 3 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Wednesday June 4 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Thursday June 5 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Friday June 6 Northbound, Right Lane near Exit 10 10 a.m. to 1 p.m.

 

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge, weather permitting. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night. An interactive map showing vessel locations on the Hudson River is now available on the project website, NewNYBridge.com, for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.  More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Rockland Landing construction
  • Westchester Landing construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Armoring of Dredge channel
  • Construction of Temporary Joint Facility at exit 12