The New York State Thruway Authority and Tappan Zee Constructors, LLC (TZC) have announced that test boring operations in the Hudson River have been completed. The borings in the river…
No new pre-construction activities are slated for the week of June 3. Environmental monitors continue to be installed in Rockland County as the New York State Thruway Authority and Tappan…
In observance of Memorial Day Weekend, Tappan Zee Constructors, LLC will not work on May 25, 26 or 27, 2013. The New York Thruway Authority and TZC, LLC would like…
Installation of the Rockland environmental monitors is scheduled to begin the week of May 20. These construction monitoring devices, which monitor vibration, noise, and air quality, will be in place…
Residents kept informed by noise, vibration and air quality monitors as first pile driving begins on a temporary work platform As work begins on a temporary Westchester work platform for…
During the week of May 13, work is expected to continue on the Westchester trestle, which is the first of the temporary work platforms to be constructed as part of…
Work is expected to begin during the week of May 6 on the Westchester trestle, which is the first of the temporary work trestles to be constructed as part of…
Soil sampling and subsurface utility explorations operations will be conducted within the Thruway’s right of ways. Soil sampling is a requirement of any project that includes excavation work, in order…
Surveying work for the New NY Bridge Project will continue during the week of April 22 as engineering crews conduct more design surveys at various locations in Rockland and Westchester…
The New York State Thruway Authority, Tappan Zee Constructors, New York State Department of Labor and the New NY Works Program will host informational events for businesses interested in learning…