Two of the new bridge’s westbound main span towers have reached their ultimate height, 419 feet above the Hudson River. Tappan Zee Constructors, LLC (TZC) is scheduled to complete all…
Tappan Zee Constructors, LLC (TZC) is preparing to realign traffic lanes in the area of the former Tarrytown toll plaza as the new bridge’s landings continue to progress. The alignment…
![img_0150lr](https://www.newnybridge.com/wp-content/uploads/2016/10/IMG_0150lr.jpg)
The New NY Bridge project reached a major milestone this week with the installation of the final steel-blue girder assembly for the new westbound approach span. The 290-foot structural steel…
Tappan Zee Constructors, LLC (TZC) has installed the final steel girder assembly for the new westbound span. More than 100 similar girder assemblies have been installed on the new approach…
![08_tzc160927p0759lr](https://www.newnybridge.com/wp-content/uploads/2016/09/08_TZC160927p0759lr.jpg)
Tappan Zee Constructors, LLC (TZC) is one step closer to completing the twin-span crossing as the new bridge’s westbound towers reach their ultimate height, 419 feet above the Hudson River….
The new bridge’s westbound towers are reaching their ultimate height, 419 feet above the Hudson River. Tappan Zee Constructors, LLC (TZC) is removing the project’s blue jump forms as the…
Periodic closures of the main navigation channel and adjacent span areas will occur due to on-going construction, with the first full closure scheduled for this Friday, Sept. 23, from 6…
![img_0993lr](https://www.newnybridge.com/wp-content/uploads/2016/09/IMG_0993lr.jpg)
Prior to the start of New NY Bridge construction in 2013, Rockland and Westchester residents living near the project site voted overwhelmingly in favor of new permanent barriers to reduce…
![tzc091416p0373lr](https://www.newnybridge.com/wp-content/uploads/2016/09/tzc091416p0373lr.jpg)
The first full closure of the main navigational channel occurred this September. Approximately 70 closures are anticipated through the end of 2017 as project crews install new sections of structural…
This week, the I Lift NY super crane installed the new eastbound span’s final structural steel girder assembly for this phase of construction. The remaining girder assemblies will be placed…