The New York State Thruway Authority and Tappan Zee Constructors, LLC (TZC) will allow all lanes to remain open from 6 a.m. on Friday, Dec. 30, to, 6 a.m. on…
Tappan Zee Constructors, LLC (TZC) continues to install the new bridge’s stay cable system. More than 70 stay cables are fully anchored and tensioned on the 419-foot main span towers….
![tzc161220_001lr](https://www.newnybridge.com/wp-content/uploads/2016/12/TZC161220_001lr.jpg)
The New NY Bridge project team is supporting local charities to make the holidays a little more joyous for those in need in our communities. Members of the New York…
![tzc161213p0147-2lr](https://www.newnybridge.com/wp-content/uploads/2016/12/TZC161213p0147-2lr.jpg)
Motorists on the Tappan Zee Bridge may be familiar with the rhythmic bumps in the existing bridge’s roadway. These interruptions are the result of nearly 200 expansion joints, which are…
Governor Andrew M. Cuomo announced that the New NY Bridge reached a major milestone this week with the final pours for the eight main span towers. The 419-foot towers stand…
![tzc161213p002lr](https://www.newnybridge.com/wp-content/uploads/2016/12/TZC161213p002lr.jpg)
Governor Andrew M. Cuomo today announced the New NY Bridge has reached a major milestone with the topping off of the eight main span towers, and with the final concrete…
New NY Bridge Project on Track to Open in 2018 and on Budget at $3.98 Billion Approximately 90 Percent of Support Structures on New NY Bridge Placed; Including 126 Steel…
Tappan Zee Constructors, LLC (TZC) will begin drainage repair operations on the southbound/eastbound New York State Thruway (I-87/I-287) tonight. Operations will continue through the overnight and early morning hours of…
![tzc161128p0499lr](https://www.newnybridge.com/wp-content/uploads/2016/12/TZC161128p0499lr.jpg)
Tappan Zee Constructors (TZC) recently installed the first of 18 overhead gantries, which will be equipped with enhanced technology to help keep traffic moving safely and efficiently on the new…
Tappan Zee Constructors (TZC) has completed installation of all road deck panels for the westbound bridge’s approaches. TZC placed nearly 3,000 steel-reinforced concrete panels, weighing as much as 74,000 pounds…