Tappan Zee Constructors, LLC (TZC) is scheduled to resume girder assembly installation on the eastbound bridge next week. TZC will place four assemblies on two piers near the Rockland landing….
Tappan Zee Constructors, LLC (TZC) will continue to install concrete noise barrier panels along the southbound New York State Thruway (I-87/I-287) in South Nyack this coming week. TZC anticipates completing…
Onlookers were treated to a brief preview of the New NY Bridge’s night-time illuminations last week as the project team held the aesthetic lighting system’s first preliminary test. The test…
The westbound span of the New NY Bridge is one step closer to coming together – quite literally. Tappan Zee Constructors recently used the I Lift NY super crane to…
Tappan Zee Constructors, LLC (TZC) has made significant progress on the main span, with more than 100 stay cables fully anchored and tensioned on the 419-foot main span towers. The…
While the project’s I Lift NY super crane continues to raise large sections of structural steel on the main span roadway, four lighter and taller cranes have proved to be…
Tappan Zee Constructors (TZC) will connect the westbound main span and Rockland approach with a 750,000-pound section of structural steel this week. The lift follows the successful installation of a…
Tappan Zee Constructors, LLC (TZC) will limit marine operations today following Thursday’s heavy snowfall. Work on the landings will continue. Select personnel will also remove snow at all project locations….
While all eight of the project’s iconic towers have reached their full height at 419 feet above the Hudson River, crews continue to work across the entire main span and…
The project’s largest crane, I Lift NY, went back to work this weekend to install a critical section of structural steel on the New NY Bridge project. The segment is…