Tappan Zee Constructors (TZC) is scheduled to continue installing steel girders for the Governor Mario M. Cuomo Bridge over River Road at the Rockland landing. The materials connect the eastbound…
Tappan Zee Constructors (TZC) this week lowered the 532-foot-long center span of the retired Tappan Zee Bridge, the first of five massive main span sections of steel to be removed…
Governor Andrew M. Cuomo today announced the 532-foot-long center span of the retired Tappan Zee Bridge – the first of five main span sections – began the process of being…
Tappan Zee Constructors (TZC) is preparing to install steel girders and concrete deck panels for the Governor Mario M. Cuomo Bridge over River Road at the Rockland landing. The materials…
The installation of precast concrete slabs near the bridge’s Westchester landing will now require an overnight closure of the northbound New York State Thruway (I-87/I-287) exit 9 (Tarrytown – Sleepy…
Tappan Zee Constructors (TZC) is getting ready to place the remaining girders for the eastbound span. Starting Monday, TZC will use land-based cranes to install nine steel girders above River…
Tappan Zee Constructors (TZC) is scheduled to continue installing new precast concrete slabs near the bridge’s Westchester landing. The work will create a new base roadway for the twin-span crossing’s…
Tappan Zee Constructors (TZC) is scheduled to remove large steel truss sections of the old bridge next week with the assistance of the project’s largest crane, dubbed I Lift NY….
The project gallery features a new selection of aerial photography, highlighting progress on the new eastbound span, as well as dismantling efforts on the old bridge. The project’s largest crane,…
The I Lift NY super crane last Thursday installed the project’s final massive steel blue girder assembly, bringing the eastbound span of the Governor Mario M. Cuomo Bridge one step…